top of page

N62473-16-C-0616

Yuma Observation Towers ~ Award amount $1,546,718.00

Three towers were designed and constructed similar to existing towers. Each tower was constructed adjacent to the existing tower. The design portion of this contract consist of 4 stages: Concept, design development, pre-final and final.  

 

All three existing towers were demolished after the new towers were operational.

 

Larco installed concrete foundations, electrical, fiber, ground grid/lighting protection, pre-engineered galvanized towers, paint, heavy duty doors and blast resistant windows.